Hawks Engineering

Cockpit — Raw Material

SASSCO procurement plan vs in-hand strips. Aggregate deficit gates monthly production capacity.

Aggregate Raw-Material Deficit: -10,334.78 Kg

Net shortfall across the SASSCO procurement plan window (Nov-25 to Jun-26). Open POs need expediting before May press kick-off.

Critical
Required Strips
41,929.5
5 parts in demand sheet
In-Hand Strips
22,254
across all grades
Coverage Ratio
53%
below 100% triggers PO expediting
Strip Requirement vs In-Hand

By demand-sheet line

Required strips
In hand (deficit)
In hand (sufficient)
Demand Sheet · SASSCO

Strip × parts-per-strip math, ledger view

PartGradeStripPPSStrips Bal.Parts Bal.OEMIn HandReq. StripsStatus
Male, Hinge Front Upper (1)
Z · SASSCO
JSC 2705×80×122015239.53,592.53,592.52,3825,974.5Short
Male, Hinge FR LWR, RH/LH (2)
Z · SASSCO
JSC 2705×185×12203836513,87013,8705,09118,961Short
Female, Hinge FR LWR, RH/LH (2)
Z · SASSCO
JSC 2705×185×122016497847845,3496,133Short
Male, Hinge RR UP RH/LH (3)
Y+G+Z · SASSCO
JSC 2704.5×97×12201600000Sufficient
Male, Hinge RR LWR RH/LH (4)
Y+G+Z · SASSCO
JSC 2704.5×85×122015705701,4299,43210,861Short