Active contractor crews
2
Mr. Ramzan · Mr. Qadir
Last 12 weeks output
62,950
Avg 5,246 / week
Open tracksheets
3
Avg age 1h 35m
Mr. Ramzan — Weekly output
WeekOutputPlanVarianceStatus
W-124,7205,400-680Below plan
W-114,8605,400-540Below plan
W-104,9105,400-490Below plan
W-95,1005,400-300Below plan
W-85,3205,400-80Below plan
W-75,2805,400-120Below plan
W-65,4105,400+10Above plan
W-55,3805,400-20Below plan
W-45,6205,400+220Above plan
W-35,4505,400+50Above plan
W-25,3905,400-10Below plan
W-15,5105,400+110Above plan