Sheets
Title
Demand Sheet — Nov-25 to Jun-26
DRAFT
Prepared by
Mr. Ahmad Bin Iqbal
Verified by
Approved by
Net shortfall
10,335 kg
SASSCO shortfall
1,271.7 kg
7 parts
DIGITAL shortfall
2,316.7 kg
5 parts
Total shortfall
3,588.4 kg
Order from approved suppliers
Per-part demand calculation (live)
PartSourceStrips balIn-processRequiredStrips reqWeight kgSheets req
Male Hinge FR UPSASSCO239.54267.5238267256.731
Female Hinge FR UPSASSCO1983120238289340.941
Male Hinge RR UPDIGITAL018402382162458.453
Female Hinge RR UPDIGITAL1215002200178504.258
Male Hinge FR LWRSASSCO882100180041157.019
Male Hinge RR LWRSASSCO1452240180028107.313
Female Hinge RR LWRDIGITAL30980120095269.231
Male Hinge FR UP (Y)SASSCO4105200320000.00
Female Hinge FR UP LHDIGITAL022002820188532.561
Male Hinge FR UP LHSASSCO2204080238260229.828
Female Hinge RR UP LHDIGITAL813802200195552.464
Male Hinge FR LWR LHSASSCO801980180047180.022