Hinge Cockpit — Overview
A 10-second read on production health across all 16 hinge parts. Numbers from this morning's ledger reconciliation.
LIVE · 10:42
Plan Attainment
40.2%
+12 pts vs last month
OEM Coverage
15 days
trending down
Behind Schedule
8 / 16
parts not started this month
WIP Negative Cells
14
parts with negative stage balance
WIP Distribution by Part
Press
Transit-1
ELP
Transit-2
Assembly
FG
Positive balance per stage (negatives excluded for clarity)
Plan Status — April 2026
16 parts in scope
7
of 16 done
Complete
7
In Process
1
Not Started
8
Karachi Dispatch — Weekly
Units shipped to OEM by product family
Needs Attention
4 critical · 3 warnings
Hinge Female RH 1 — negative balance in 3 stages
Press: -394 · Transit-1: -330 · Assembly WIP: -106
2h ago
Hinge Male RH 1 — negative balance in 1 stage
Assembly WIP: -108
2h ago
Hinge Female LH 1 — negative balance in 1 stage
Transit-1: -350
2h ago
Hinge Male LH 1 — negative balance in 1 stage
Press: -41
2h ago
Plan vs Actual — All 16 Parts
Plan
Actual
Current month closeout